The project objective and scope

National Air Traffic Services (NATS) provides air navigation services to the United Kingdom and to internationally agreed areas outside the UK. In the mid eighties, it could be observed that air travellers were increasingly experiencing delays to their schedules, and so NATS attempted to introduce major changes to their air traffic control centre at West Drayton. However, this attempt ran into much difficulty and further studies showed that the West Drayton facility would run out of capacity by 1996. Therefore NATS motioned to replace the facility, that had little room for expansion to meet future demand, with a new facility on a greenfield site in Swanwick.

This facility would become the new London Area and Terminal Control Centre (LATCC) and the proposal aimed to produce 40% additional capacity to accommodate the delays that NATS were currently facing. The project not only involved a new site but a new software system that claimed to be "more advanced than anything that is being tried anywhere in the world." The software was to be based on that of a similar project in the US, therefore minimising technological risk. The project was set up as a fixed price contract with a cost of £350 million.

Project life Cycle

The initiation phase of this project began back in 1988 with a solid proposal and reasoning for the project. As we know, project success depends on effective ‘front-end phases' though, and feasibility for this project was not be tested. Although it used a specially-selected NATS committee, the project appeared to lack adequate consultation with staff members. The new Swanwick centre proposed an overly optimistic opening date of 1996.

The planning phase took 3 years to complete, with building beginning in 1991. Throughout this time, expenditure and an idealistic timeframe was agreed upon. The report lacks details as to how this project plan was assessed or appraised. Subsequent problems led to constant revision and appraisal of the original plan. There is no specification in the report to provide identification of each member's tasks, penalties for delay in completion and amount of risk analysis completed for any problems faced. However the team was flexible in its response to incurred delays.

These delays became all too apparent during the execution and controlling phase. Construction was completed on time by 1994. Problems starting to accrue during systems implementation with NATS acceptance of the NERC system halted from Nov 1995 to June 1997 and delayed even further to March 1998 following training and development issues. Further political disputes and a merger with Lockheed Martin fuelled more testing and review, altering the original plan beyond recognition. The completion date was delayed further to Winter 1999/2000 with a current target date for first operations resting on 30th March 2008. Closure of this project may be somewhat of a relief to the administrators, who have some...

Find Another Essay On Swanwick Airport Case Study

BAE Automated Systems Case Study

2920 words - 12 pages attractiveness of businesses that were swarming to it. Issues with handling high traffic volume, disruptions in connection schedules, and an overall poor airport layout led the city of Denver to decide whether they wanted to expand or replace the Stapleton Airport. A study performed in 1983 determined that an expansion of Stapleton’s capacity was needed. In the mid

Kona Airport: A Potential Gateway to Success

1177 words - 5 pages , the potential to study abroad could be made possible by cheaper international flights with the addition of international partners. There are those who might view the expansion as an unnecessary change, when in fact it is crucial. According to Congresswoman Tulsi Gabbard, “This is not an area that it’s a luxury, but one that is essential for business, for healthcare, for education” (Video). In another instance, the Kona Airport expansion may be

Description of Clinical Leadership Theories

2073 words - 8 pages vision of the future. In addition, the various differences between management and leadership are also highlighted in relation to clinical leadership. Works Cited Bass, B. M., & Bass, R. (2009). The Bass handbook of leadership: Theory, research, and managerial applications. London, UK: Simon and Schuster. Bell, M. (2009). Enacting servant leadership: A case study for building congruence and capacity. Saarbrucken, DE: LAP Lambert Academic

Analysis of Great Lakes Airlines’ Portfolio

2415 words - 10 pages Airport (n.d.). ATL Fact Sheet. Retrieved from http://www.atlanta-airport.com/Airport/ATL/ATL_Factsheet.aspx Hartsfield –Jackson Atlanta International Airport (n.d.). Case Study. Airport Master Plan – Demand/Capacity Analysis and Facility Requirements Summary. Retrieved from http://www.atlanta-airport.com/Airport/MasterPlan/ATL-FacReqts-DRAFT-Summary-101113.pdf Hartsfield –Jackson Atlanta International Airport (n.d.). Case Study

Airport Security

1538 words - 6 pages PROBLEMS IN AIRPORT SECURITY The crash of TWA Flight 800 combined with increased terrorism in airports had led to more rigid security measures. Anyone who has flown recently has discovered that at most airports when you want to get your boarding pass, you must show a picture identification. This same procedure is followed when checking your baggage outside the terminal building. Considering the bombing of the World Towers, the Federal

supershuttle

1325 words - 5 pages and more than 50 cities, moreover, the firm has around 1,200 vans on the road. (http://www.supershuttle.com/AboutUs.aspx) It does not have any regular times or any routes, any customer who wants to use their service should phone or make a reservation on line.Although SuperShuttle is a successful organisation, it also experiences a range of issues. This case study aims to explore the problems that SuperShuttle faced, and then analysing these

supershuttle

1325 words - 5 pages and more than 50 cities, moreover, the firm has around 1,200 vans on the road. (http://www.supershuttle.com/AboutUs.aspx) It does not have any regular times or any routes, any customer who wants to use their service should phone or make a reservation on line.Although SuperShuttle is a successful organisation, it also experiences a range of issues. This case study aims to explore the problems that SuperShuttle faced, and then analysing these

Advantages and Problems for a City Being a Transport Hub

2554 words - 10 pages park in it. China.org.cn. Retrieved from http://www.china.org.cn/business/2011-04/12/content_22337389.htm Shen, Q. and Pan, H. (2010).Intermodal Transfer Between Bicycles and Rail Transit in Shanghai, China. Journal of the Transportation Research Board, 2010, 181-188. Shen, J. and Wu, F. (2013). The Development of Master-Planned Communities in Chinese Suburbs: A Case Study of Shanghai's Thames Town. Urban Geography, 33 (2), 183-203. Shen, Z

Cartwright-Porter Regional Airport

915 words - 4 pages management philosophy. The HR director/manager is the face for the company policy and the voice of the philosophy. Vigilance and zero tolerance are ways a company can limit problems of sexual harassment. Sexual harassment issues are one of the most vexing of problems that can and must be dealt within the working environment. The simulation's approach of a short and long-term dual format was a typical case study presentation that seriously lacked the

Airline Portfolio: Delta Air Lines Analysis

1856 words - 7 pages /delta-air-lines-marketing_b_3197987.html Hartsfield –Jackson Atlanta International Airport (n.d.). ATL Fact Sheet. Retrieved from http://www.atlanta-airport.com/Airport/ATL/ATL_Factsheet.aspx Hartsfield –Jackson Atlanta International Airport (n.d.). Case Study. Airport Master Plan – Demand/Capacity Analysis and Facility Requirements Summary. Retrieved from http://www.atlanta-airport.com/Airport/MasterPlan/ATL-FacReqts-DRAFT-Summary

British Airways Case Study

3464 words - 14 pages leader of airline marketing. For this reason, the most important major find the position of whole market for the British Airways. In this essay, firstly, I would introduce some academic articles, which can help people more clearly to understand this topic. Second extent to a discussion of the case study methodology; include why it is useful and limitation of it. Next, I could describe the case study which I might use two models; the main model

Similar Essays

Delta Air Lines Airport & Airspace Capacity Case Study

1501 words - 7 pages Allegiant Air’s main focus area and home base location is Las Vegas, Nevada. McCarran International Airport services the Las Vegas area, but it is nearing capacity. Since McCarran is an urban area, expansion is not a viable option. This case study shows that McCarran International Airport can implement short term improvements to handle additional capacity, but the airport has a capacity ceiling that will be hit in the next 5 to 15 years. A

Delta Air Lines Airport & Airspace Capacity Case Study

1282 words - 6 pages ). Works Cited Hartsfield –Jackson Atlanta International Airport (n.d.). ATL Fact Sheet. Retrieved from http://www.atlanta-airport.com/Airport/ATL/ATL_Factsheet.aspx Hartsfield –Jackson Atlanta International Airport (n.d.). Case Study. Airport Master Plan – Demand/Capacity Analysis and Facility Requirements Summary. Retrieved from http://www.atlanta-airport.com/Airport/MasterPlan/ATL-FacReqts-DRAFT-Summary-101113.pdf Hartsfield –Jackson

Delta Air Lines Airport & Airspace Capacity Case Study

1655 words - 7 pages resources. This case study elaborates on how the four airports expanded their capacities to accommodate the country’s economic growth. Toronto Pearson International Airport (IATA code YYZ) YYZ is Canada’s largest airport in terms of passenger traffic and aircraft movement. In 2012, YYZ handled over 34 million passengers and over 435,000 aircraft movements. It is the largest out of the four Air Canada hubs. Not only does the airport serve the city of

London Heathrow Airport Essay

1099 words - 4 pages by privatized company formerly known as British Airport Authority (BAA plc), now Heathrow Airport Holdings. Heathrow Airport Holdings owns and operates four major airports in the UK, including London Heathrow, Aberdeen, Glasgow and Southampton. However, in this case study, London Heathrow would be the writer’s main interest as to look at the effect of its privatization and find the possible impacts that it might have on the economy and society